Foothills Trail - Bridge #PRT17196-B Replacement (Program No. 6159)

ProjectHeaderPhoto.jpg

What's Happening

Pierce County issued the Notice to Proceed for July 31, 2017.  The Contractor, Prospect Construction, Inc., will be on site performing the following work:
  • Installing erosion control measures
  • Clearing, grubbing, and demolishing the existing abutments
  • Excavating for the new culvert

About the Project


This contract replaces and improves the Foothills Trail Bridge No. PRT17196-B (Program No. 6159), near South Prairie, which was damaged by a falling tree in 2014.  The work calls for a 51-foot span plate arch replacement bridge, spiral nail walls, welded wire walls, and other work.

Project Timeline


June 09, 2017:  Bid Opening held

June 22, 2017:  Pierce County awarded the contract to Prospect Construction, Inc.

July 20, 2017:  Pierce County hosted the Pre-construction Meeting

July 31, 2017:  Pierce County issued the Notice to Proceed

January 2018:  Anticipated Substantial Completion

Winter/Spring/Summer 2018:  Plant establishment period

December 2018:  Anticipated Physical Completion
Contact Us
Send a message arrow
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Prospect Construction, Inc.
Contractor
Phone: (253) 446-1600
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
116 23rd Street Southeast
Puyallup, WA 98372