C Street South - ADA Improvements (CRP 5860)

What's Happening

 
Engineering: 
We're beginning the design engineering for the project.  Currently we're gathering information about the existing conditions and coordinating with utility companies.

Land:  All improvements are expected to fit within the existing right-of-way.

Survey:  County surveyors will be in the area gathering field data of the project area.

About the Project

 


Planned improvements to C Street South from Wheeler Street South to 112th Street South (CRP 5860) are intended to improve ADA accessibility and sidewalk connectivity in the project area.  The improvements would include the following:
  • Installing new sidewalk on both sides of C Street South between Lafayette Street South and 112th Street South.
  • Installing new curb ramps at each intersection from Wheeler Street South through Lafayette Street South.

Project Timeline 


June 2017 to January 2018:  
Gathering of field data; Design Engineering; Development of construction plans, specifications, and estimate. 

Spring 2018:  Construction begins.
Contact Us
Send a message arrow
Gregory Hess, P.E.
Design Supervisor
Phone: (253) 798-2283
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409